qesp2 reports

Quality Education Support Programme II

Weekly reporting dashboard

Public view of the activity map, weekly minutes, expert updates, evidence gaps, and source documents.

Upload weekly data
Activities120
Active103
Pending63
In process17
Completed12
Budget€10,659,995

Weekly upload watchlist

  • Loiq MirovRequired weekly upload missing for the current week.Last upload: none; last activity mention: 2026-05-04
  • Danylo AnishchenkoRequired weekly upload missing for the current week.Last upload: none; last activity mention: 2026-05-04
  • Nigora LashkarovaRequired weekly upload missing for the current week.Last upload: none; last activity mention: 2026-05-04

Activity stream

Filter is stored in the URL, so the selected expert survives reloads.

2026-05-15activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-15

  • This is a test weekly report submission from automated browser testing.
  • Test evidence summary - nothing real just testing the form.
Next actions
  • Continue with normal operations.
2026-05-14activityIn Process

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Aigul Kazzhanova · Aigul Kazzhanova weekly upload | 2026-05-14

  • test123
  • test123
Next actions
  • test123
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Isolated systemd production deploy validation 1778910626593
  • Final isolated systemd-run deploy test: endpoint updated YAML, committed, pushed, built, and uploaded production from a clean unit.
Next actions
  • Production curl should find this exact phrase after 40 seconds.
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Cache-cleared automatic production deploy validation 1778910452243
  • Cache-cleared automatic deploy test: the submission endpoint committed data, pushed git, rebuilt static output, and uploaded production.
Next actions
  • Production curl should find this exact phrase after Cloudflare propagation.
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Successful browser validation build upload workflow 1778910301547
  • Successful browser test evidence: preview UI updated YAML, committed, pushed, built static pages, and uploaded production.
Next actions
  • No action; production curl should find this phrase.
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Final browser validation build/upload workflow 1778910259512
  • Final browser test evidence: preview UI updated YAML, committed, pushed, built static pages, and uploaded production.
Next actions
  • No action; validation complete once production curl finds this phrase.
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Browser validation after split build/upload deployment workflow 1778910201394
  • Browser test evidence: preview UI submitted YAML, committed and pushed data, then ran bun run build and bun run upload for production.
Next actions
  • Confirm production static page contains this final browser-submitted report.
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Browser UI validation after adding build and deploy steps to weekly submission workflow.
  • Browser test evidence: preview UI submitted YAML, committed and pushed data, then ran production build and deploy.
Next actions
  • Verify production static site contains this browser-submitted report.
2026-05-11activityOn Track

IP1: IP1. Mobilisation of the Project Team and Project Office Set Up

Stefan Siewert · Stefan Siewert weekly upload | 2026-05-11

  • Test submission by Stefan Siewert to validate automatic YAML commit and production deployment after removing workerd.
  • Validation evidence generated by automated test submission on the Node preview server.
Next actions
  • Confirm production static site includes this submission after Cloudflare build.
2026-05-04highlight

Weekly highlight

Stefan Siewert · Weekly Staff Meeting Minutes | 4 May 2026

  • Bavarian strategic cooperation agreement with MoLME advanced a 50-person exchange programme.
2026-05-04highlight

Weekly highlight

Stefan Siewert · Weekly Staff Meeting Minutes | 4 May 2026

  • EUD comments on Draft Progress Report 2025 were received and addressed.
2026-05-04highlight

Weekly highlight

Stefan Siewert · Weekly Staff Meeting Minutes | 4 May 2026

  • Cristina Rimini mission continued on quality monitoring across REMC, RTTI, and NTC PISA teams.
2026-05-04highlight

Weekly highlight

Stefan Siewert · Weekly Staff Meeting Minutes | 4 May 2026

  • Humanities Formative Assessment workshop trained 84 primary teachers.
2026-05-04highlight

Weekly highlight

Stefan Siewert · Weekly Staff Meeting Minutes | 4 May 2026

  • QESP II showcased EU-supported education reforms at EU Day 2026.
2026-05-04componentON TRACK

C4-6 Budget Support Programme

Nigora Lashkarova · Weekly Staff Meeting Minutes | 4 May 2026

  • External audit debrief completed at MoF.
  • All four VET and Adult Training indicators confirmed compliant.
Next actions
  • Prepare audit findings summary for progress report.
2026-05-04componentON TRACK

C3 Governance

Stefan Siewert · Weekly Staff Meeting Minutes | 4 May 2026

  • Output 3.2 documents submitted to EUD.
  • Logframe OVI revision required per EUD feedback.
Next actions
  • Support EUD and Eductrade decision-making on LogFrame update.
2026-05-04componentN/A

C2 Labour Market

Loiq Mirov · Weekly Staff Meeting Minutes | 4 May 2026

  • Tracer Survey remained at 98 percent completion with data cleaning in progress.
  • LFS second-round budget negotiations ongoing with Agency of Statistics.
Next actions
  • Complete Tracer Survey data entry by 2026-05-30.
2026-05-04componentMONITOR

C1b TVET & PPP

Danylo Anishchenko · Weekly Staff Meeting Minutes | 4 May 2026

  • Regional trainings finalized for Bokhtar and Khujand.
  • Coordination meeting held with EUD and TVET Committee Chair.
  • NKE Carmen Rotaru mission in preparation.
Next actions
  • Execute two 3-day trainings in Bokhtar and Khujand by 2026-05-31.
2026-05-04componentON TRACK

C1a PISA & Assessment

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 4 May 2026

  • Nine meetings held with REMC, UNESCO, UNICEF, RTTI, MoES, NTC, and School #93.
  • Humanities FA workshop conducted with strong teacher engagement.
  • Quality assurance monitoring framework discussed with international expert.
Next actions
  • Finalize Cristina Rimini mission.
  • Develop infographic on assessment and quality assurance.
  • Coordinate REMC, RTTI, and MoES on data-use training.
2026-04-27highlight

Weekly highlight

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 27 April 2026

  • EU evaluator rated BSP implementation among the strongest in the EU portfolio.
2026-04-27highlight

Weekly highlight

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 27 April 2026

  • Component 3 submitted revised Logframe OVIs, AI-First Readiness Memorandum, and LEG.TJ recommendations.
2026-04-27highlight

Weekly highlight

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 27 April 2026

  • Cristina Rimini mission started on education quality monitoring with REMC, RTTI, and NTC PISA teams.
2026-04-27highlight

Weekly highlight

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 27 April 2026

  • Formative Assessment workshop reached 84 primary school teachers at Secondary School #53.
2026-04-27highlight

Weekly highlight

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 27 April 2026

  • Eductrade coordination mission held high-level meetings with TVET Committee, MoES, and EUD.
2026-04-27componentON TRACK

C4-6 Budget Support Programme

Nigora Lashkarova · Weekly Staff Meeting Minutes | 27 April 2026

  • External audit debrief concluded at Ministry of Finance.
  • Evaluator Oliver Desay gave positive BSP performance assessment.
Next actions
  • Monitor EU audit document exchange on a rolling basis.
2026-04-27componentON TRACK

C3 Governance

Stefan Siewert · Weekly Staff Meeting Minutes | 27 April 2026

  • Three strategic documents submitted to EUD.
  • Initial LEG.TJ platform recommendations advanced.
Next actions
  • Follow up with EUD on review timeline by 2026-04-30.
2026-04-27componentN/A

C2 Labour Market

Loiq Mirov · Weekly Staff Meeting Minutes | 27 April 2026

  • Loiq was on authorised mission with backstop handover completed.
  • Tracer Survey reached 98 percent completion; data cleaning in progress.
Next actions
  • Finalize Tracer Survey data entry by 2026-04-30.
2026-04-27componentMONITOR

C1b TVET & PPP

Danylo Anishchenko · Weekly Staff Meeting Minutes | 27 April 2026

  • Mission meeting with TVET Committee Chair covered nationwide rollout of methodological centres.
  • Regional workshops planned for Khujand and Bokhtar.
Next actions
  • Finalize workshop planning by 2026-04-30.
2026-04-27componentON TRACK

C1a PISA & Assessment

Aigul Kazzhanova · Weekly Staff Meeting Minutes | 27 April 2026

  • FA workshop completed with 84 primary school teachers.
  • National expert contracts signed for Sherali G. and Kholis S.
  • Cristina Rimini arrived and held the RTTI inception meeting.
Next actions
  • Coordinate joint workplan for Cristina Rimini mission by 2026-04-30.
  • Finalize technical workplan with RTTI and REMC by 2026-04-30.

Activity master list

120 of 120 activities shown.

IP1ACTIVE

IP1. Mobilisation of the Project Team and Project Office Set Up

Outcome n/aOutput n/aClosed (Inception)€52,000
AV
IP2ACTIVE

IP2. Organisation of Kick-off Meeting

Outcome n/aOutput n/aClosed (Inception)€45,000
EV
IP3ACTIVE

IP3. Mapping Stakeholders

Outcome n/aOutput n/aClosed (Inception)€45,000
GN
IP4ACTIVE

IP4. Organisation of Coordination Meetings with Key Stakeholders

Outcome n/aOutput n/aClosed (Inception)€45,000
EV
IP5ACTIVE

IP5. Development of Communication Strategy and Project Website

Outcome n/aOutput n/aClosed (Inception)€45,000
SP
IP6ACTIVE

IP6. Preparation of Inception Report

Outcome n/aOutput n/aClosed (Inception)€60,000
GN
PISA-Reimb-Y1ACTIVE

Year 1 Reimbursement for supporting PISA Center Operations

Outcome n/aOutput n/aAnnual Reimbursement€482,333
OP
PISA-Reimb-Y2ACTIVE

Year 2 Reimbursement for supporting PISA Center Operations

Outcome n/aOutput n/aAnnual Reimbursement€482,333
OP
PISA-Reimb-Y3ACTIVE

Year 3 Reimbursement for supporting PISA Center Operations

Outcome n/aOutput n/aAnnual Reimbursement€482,333
OP
1.1.1.2ACTIVE

Activity 1.1.1.2: Carrying out Capacity Needs Analysis, Preparation of Capacity Building Plan, PISA Programme Implementation Plan

Outcome 1Output 1.1Pending / 2026-27€48,250
MTSP
1.1.1.3ACTIVE

Activity 1.1.1.3: Implementation of Complementary Capacity Building Actions

Outcome 1Output 1.1Completed€53,600
GN
Drive folder
1.1.1.4ACTIVE

Activity 1.1.1.4: Organisation of Launch Event

Outcome 1Output 1.1Pending / 2026-27€78,250
GN
1.1.1.5ACTIVE

Activity 1.1.1.5: Conducting 1st Review Phase

Outcome 1Output 1.1Pending / 2026-27€21,000
MT
1.1.1.6ACTIVE

Activity 1.1.1.6: Conducting 1st Trial Preparation Phase

Outcome 1Output 1.1Pending / 2026-27€23,320
GN
1.1.1.7ACTIVE

Activity 1.1.1.7: Supporting Field Trial Phase

Outcome 1Output 1.1Pending / 2026-27€72,400
MR
1.1.1.8ACTIVE

Activity 1.1.1.8: Conducting 2nd Review Phase

Outcome 1Output 1.1Completed€76,790
MT
Drive folder
1.1.1.9ACTIVE

Activity 1.1.1.9: Supporting Main Survey Preparation Phase

Outcome 1Output 1.1Completed€21,000
MT
Drive folder
1.1.1.10ACTIVE

Activity 1.1.1.10: Supporting Main Survey Implementation Phase

Outcome 1Output 1.1Completed€76,790
MT
Drive folder
1.1.1.11ACTIVE

Activity 1.1.1.11: Review and Reporting Phase

Outcome 1Output 1.1Completed€76,102
MT
Drive folder
1.1.1.12NEW

Activity 1.1.1.12: Training of 50 Master Trainers

Outcome 1Output 1.1New (Add 3) — Pending€82,500
TR
1.1.1.13NEW

Activity 1.1.1.13: Training of 1206 Teachers

Outcome 1Output 1.1New (Add 3) — Pending€499,280
TR
1.1.2ACTIVE

Activity 1.1.2: Identification of Policy Priorities based on the analysis of PISA 2025 results

Outcome 1Output 1.1Pending / 2026-27€127,990
MTSP
1.1.3ACTIVE

Activity 1.1.3: Supporting Institutional arrangements on quality of education and Organisation of Capacity Building Seminars

Outcome 1Output 1.1Pending / 2026-27€110,920
TR
1.1.4ACTIVE

Activity 1.1.4: Updating the Concept on National Learning Assessments

Outcome 1Output 1.1Pending / 2026-27€93,868
MTSP
1.2.1ACTIVE

Activity 1.2.1: Development of Modules Programme and Learning Materials on Assessment Standards in line with the priorities in Concept on NLA

Outcome 1Output 1.2Pending / 2026-27€120,000
MTCMSP
1.2.2ACTIVE

Activity 1.2.2: Training Master Trainers

Outcome 1Output 1.2Pending / 2026-27€60,000
TR
1.2.3ACTIVE

Activity 1.2.3: Piloting and Scaling-up of the Modular Programme

Outcome 1Output 1.2Completed€60,000
SPAV
Drive folder
1.3.1ACTIVE

Activity 1.3.1: Developing learning and teaching materials and formative assessment tools for two subjects

Outcome 1Output 1.3In Process€140,000
MTCM
Drive folder
1.3.1NEW

Activity 1.3.1.1 TA for 10-grade assessment

Outcome 1Output 1.3New (Add 3) — Pending€51,790
MT
Drive folder
1.3.2DELETED

Activity 1.3.2: Developing methodologies for teaching and learning of selected foreign languages and Training Master trainers

Outcome 1Output 1.3Removed (Add 3)€125,000
No evidence family
1.3.3DELETED

Activity 1.3.3: Scaling up the language training

Outcome 1Output 1.3Removed (Add 3)€60,000
No evidence family
1.3.4ACTIVE

Activity 1.3.4: Developing Training Programme for IVET Teachers

Outcome 1Output 1.3Pending / 2026-27€100,000
TRCMSP
1.3.5ACTIVE

Activity 1.3.5: Developing Handicraft Programme for IVET students

Outcome 1Output 1.3Pending / 2026-27€85,000
CMSP
1.3.6ACTIVE

Activity 1.3.6: Support in identifying and implementing pilot projects in inclusive education targeting the students with special needs

Outcome 1Output 1.3Pending / 2026-27€85,000
OP
1.4.1ACTIVE

Activity 1.4.1: Developing standards and modular competence-based curricula for VET qualifications in selected sectors (in total 20)

Outcome 1Output 1.4Completed€375,800
CM
Drive folder
1.4.2ACTIVE

Activity 1.4.2. Developing a methodological guide and materials for standard development, CB curricula, digital content

Outcome 1Output 1.4Pending / 2026-27€195,000
CM
1.4.3ACTIVE

Activity 1.4.3. Supporting the development / testing of packages of materials for teaching those with special educational needs for the 3 professions

Outcome 1Output 1.4In Process€225,000
CM
Drive folder
1.4.4ACTIVE

Activity 1.4.4. Providing support to digitalisation for at least 5 out of 20 high-priority PVET professions

Outcome 1Output 1.4In Process€92,200
OP
Drive folder
1.5.1ACTIVE

Activity 1.5.1. Developing in-service training programme and learning materials on occupational standards and modular competence-based curricula

Outcome 1Output 1.5Pending / 2026-27€104,000
TRCMSP
1.5.2ACTIVE

Activity 1.5.2. Supporting the delivery of teacher in-service training for designing modular competence-based curricula and standards

Outcome 1Output 1.5In Process€141,000
TRCM
Drive folder
1.5.3ACTIVE

Activity 1.5.3. Providing methodological and other necessary support of the relevant PVET institutions and ATCs in development of digital content

Outcome 1Output 1.5In Process€90,000
OP
Drive folder
1.5.4ACTIVE

Activity 1.5.4. Strengthening the capacity of MoLME and providing methodological and other necessary support to teachers and trainers of the relevant PVET institutions and ATCs in applying digital training techniques for at least one academic year

Outcome 1Output 1.5Pending / 2026-27€90,000
TR
1.6.1ACTIVE

Activity 1.6.1. Facilitating the establishment of a multi-stakeholder Task force

Outcome 1Output 1.6Pending / 2026-27€78,000
GN
1.6.2ACTIVE

Activity 1.6.2. Drafting of a roadmap for establishing a full-fledged partnership

Outcome 1Output 1.6Pending / 2026-27€149,500
SPAV
1.6.3ACTIVE

Activity 1.6.3. Supporting to identify institutions to establish and pilot of public-private partnerships (PPP)

Outcome 1Output 1.6In Process€156,000
OP
Drive folder
1.6.4ACTIVE

Activity 1.6.4. Supporting the established PPPs to set up and pilot work-based learning (WBL) programmes and in-service training programme

Outcome 1Output 1.6In Process€190,000
TRSPAV
Drive folder
1.6.5ACTIVE

Activity 1.6.5. Facilitating organisation of the works of at least 2 Sectoral Committee(s) established

Outcome 1Output 1.6Pending / 2026-27€76,500
EV
2.1.1ACTIVE

Activity 2.1.1. Implementation of LMIS baseline study

Outcome 2Output 2.1Pending / 2026-27€54,000
MT
2.1.2ACTIVE

Activity 2.1.2. Formulation of recommendations and a multi-annual action plan for the improvement of existing LMIS

Outcome 2Output 2.1Pending / 2026-27€72,000
SP
2.1.3ACTIVE

Activity 2.1.3. Setting-up Labour Market Observatory (LMO) and preparation of workplan for LMO

Outcome 2Output 2.1Completed€125,000
AV
Drive folder
2.1.4.1ACTIVE

Activity 2.1.4.1. Reviewing the existing systems, practice and needs and Making a proposal on the LMIM

Outcome 2Output 2.1Pending / 2026-27€52,000
MTSP
2.1.4.2ACTIVE

Activity 2.1.4.2. Supporting the Agency in procuring and developing a tailor-made software programme for the LMIM

Outcome 2Output 2.1Pending / 2026-27€35,000
CMSP
2.2.1ACTIVE

Activity 2.2.1. Facilitating two rounds of LFS Reimbursement for the first round

Outcome 2Output 2.2In Process€165,000
GN
Drive folder
2.2.1ACTIVE

Activity 2.2.1. Facilitating two rounds of LFS Reimbursement for the second round

Outcome 2Output 2.2In Process€165,000
GN
Drive folder
2.2.2ACTIVE

Activity 2.2.2. Implementation of a School to Work Transition Survey

Outcome 2Output 2.2Pending / 2026-27€101,250
MT
2.2.3ACTIVE

Activity 2.2.3. Organisation of a series of trainings on how the data through LFS is used for policy planning and evaluation

Outcome 2Output 2.2Pending / 2026-27€90,000
TRSP
2.2.4ACTIVE

Activity 2.2.4. Reviewing the existing regulatory and legislative framework for remote work and make proposals for improvement

Outcome 2Output 2.2Pending / 2026-27€67,500
MTSP
2.3.1.1ACTIVE

Activity 2.3.1.1. Development of Establishment Skills Survey

Outcome 2Output 2.3In Process€87,350
MT
Drive folder
2.3.1.2ACTIVE

Activity 2.3.1.2. Implementation of two rounds of Establishment (enterprise) skills survey

Outcome 2Output 2.3In Process€100,450
MT
Drive folder
2.3.1.3ACTIVE

Activity 2.3.1.3. Organisation of series of trainings for implementing institutions

Outcome 2Output 2.3Pending / 2026-27€26,206
TR
2.3.2.1ACTIVE

Activity 2.3.2.1. Development of Skills Foresight

Outcome 2Output 2.3Pending / 2026-27€69,880
MT
2.3.2.2ACTIVE

Activity 2.3.2.2. Implementation of Skills Foresight in a selected sector and organisation of formal stakeholder consultation events

Outcome 2Output 2.3Completed€69,880
EVMT
Drive folder
2.3.2.3ACTIVE

Activity 2.3.2.3. Preparation of report on sectoral foresight and organisation of a workshop

Outcome 2Output 2.3Completed€30,571
TRMT
Drive folder
2.3.3.1ACTIVE

Activity 2.3.3.1. Development of Tracer Survey

Outcome 2Output 2.3Pending / 2026-27€81,145
MT
2.3.3.3ACTIVE

Activity 2.3.3.3. Organisation of a series of training activities for VET providers

Outcome 2Output 2.3Pending / 2026-27€116,085
TR
2.3.3.4ACTIVE

Activity 2.3.3.4. Producing relevant publications and methodical guidance related to the graduates’ tracer survey

Outcome 2Output 2.3Pending / 2026-27€59,305
MT
2.3.3.5ACTIVE

Activity 2.3.3.5. Organisation of a series of workshops

Outcome 2Output 2.3Pending / 2026-27€41,835
TR
2.3.3.6ACTIVE

Activity 2.3.3.6. Developing proposals on follow up and further replication of tracer surveys in Tajikistan

Outcome 2Output 2.3Pending / 2026-27€42,293
MTCMSP
2.3.4ACTIVE

Activity 2.3.4. Child Labour Survey

Outcome 2Output 2.3Pending / 2026-27€85,000
MT
3.1.1ACTIVE

Activity 3.1.1. Economic analysis of different International Funding Models for VET and higher education

Outcome 3Output 3.1Pending / 2026-27€50,800
MT
3.1.2ACTIVE

Activity 3.1.2. Comparative analysis of International Incentives for Performance Based Funding models for vocational and higher education

Outcome 3Output 3.1Pending / 2026-27€42,500
MT
3.1.3ACTIVE

Activity 3.1.3. Revise funding schemes and arrangements in VET

Outcome 3Output 3.1Pending / 2026-27€19,200
GN
3.1.4ACTIVE

Activity 3.1.4. Reviewing the current funding in VET institutions and developing a proposal on a new per capita based funding formula

Outcome 3Output 3.1Pending / 2026-27€42,500
MTCMSP
3.1.5ACTIVE

Activity 3.1.5. Reviewing the current funding scheme in higher education and developing a proposal on a new equitable funding scheme

Outcome 3Output 3.1Pending / 2026-27€30,000
MTCMSP
3.2.1.1ACTIVE

Activity 3.2.1.1. Designing an ex-ante and ex-post impact assessment for relevant project components

Outcome 3Output 3.2Pending / 2026-27€75,230
MT
3.2.1.2ACTIVE

Activity 3.2.1.2. Organisation of training on M&E

Outcome 3Output 3.2Pending / 2026-27€22,130
TR
3.2.1.3ACTIVE

Activity 3.2.1.3. Supporting beneficiaries’ monitoring, evidence collection and reporting processes

Outcome 3Output 3.2Pending / 2026-27€97,360
OP
3.2.2ACTIVE

Activity 3.2.2. Providing a help-desk function for government officials

Outcome 3Output 3.2Pending / 2026-27€230,120
GN
3.2.3ACTIVE

Activity 3.2.3. Organisation of training and coaching the staff for preparation of funding proposals

Outcome 3Output 3.2In Process€53,105
TRSP
3.2.4ACTIVE

Activity 3.2.4. Organisation of international peer learning visits

Outcome 3Output 3.2In Process€53,105
MR
Drive folder
3.2.5ACTIVE

Activity 3.2.5. Organisation of international thematic conferences

Outcome 3Output 3.2Pending / 2026-27€65,065
TR
Support-Y1ACTIVE

Year 1 reimbursement for support activities

Outcome n/aOutput n/aAnnual Reimbursement€90,000
OP
Support-Y2ACTIVE

Year 2 reimbursement for support activities

Outcome n/aOutput n/aAnnual Reimbursement€90,000
OP
Support-Y3ACTIVE

Year 3 reimbursement for support activities

Outcome n/aOutput n/aAnnual Reimbursement€90,000
OP
Support-Y4ACTIVE

Year 4 reimbursement for support activities

Outcome n/aOutput n/aAnnual Reimbursement€90,000
OP
Support-Y5ACTIVE

Year 5 reimbursement for support activities

Outcome n/aOutput n/aAnnual Reimbursement€90,000
OP
3.2.7ACTIVE

Activity 3.2.7. Assisting Ministry of Education and Science in coordinating the activities related to the Global Partnership for Education

Outcome 3Output 3.2In Process€88,510
GN
Drive folder
3.2.8ACTIVE

Activity 3.2.8. Supporting MoLME in the development of the National Strategy/Concept/ Programme up to 2030

Outcome 3Output 3.2Completed€79,660
SP
Drive folder
3.3.1ACTIVE

Activity 3.3.1. Assisting the EUD in organising and planning the QESP II Programme Steering Committee meetings

Outcome 3Output 3.3In Process€34,625
EVSP
Drive folder
3.3.2ACTIVE

Activity 3.3.2. Supporting the EUD in monitoring the implementation of the QESP II programme

Outcome 3Output 3.3Pending / 2026-27€96,430
SP
3.3.3DELETED

Activity 3.3.3. Supporting the EUD in the development and implementation of a M&E framework

Outcome 3Output 3.3Removed (Add 3)€128,570
No evidence family
3.3.4ACTIVE

Activity 3.3.4. Supporting the EUD in the processes and procedures, related to the future EU budget support intervention in the VET and labour sectors

Outcome 3Output 3.3Pending / 2026-27€64,285
OP
4.1.1ACTIVE

Activity 4.1.1.1 Needs assessment with staff of MoLME, PVETs and ATCs

Outcome 4Output 4.1Pending / 2026-27€71,640
MT
4.1.2.1ACTIVE

Activity 4.1.2.1. Developing Business Requirement document (BRD) for IMS compatible with the LMIS in terms of architecture and work/data flows

Outcome 4Output 4.1Pending / 2026-27€28,656
CM
4.1.2.2ACTIVE

Activity 4.1.2.2. Organising a workshop with MoLME staff to validate the BRD

Outcome 4Output 4.1Pending / 2026-27€10,000
TR
4.1.2.3ACTIVE

Activity 4.1.2.3. Developing Technical specifications and a Tender Dossier

Outcome 4Output 4.1Pending / 2026-27€9,104
CM
4.1.3.1ACTIVE

Activity 4.1.3.1. Assisting MoLME for tendering process (evaluation of the bids, selection of best service providers etc.)

Outcome 4Output 4.1Pending / 2026-27€25,074
GN
4.1.3.2ACTIVE

Activity 4.1.3.2. Following up the implementation of the IMS development and procurement of goods and services with the selected service providers

Outcome 4Output 4.1Pending / 2026-27€21,492
GN
4.1.3.3ACTIVE

Activity 4.1.3.3. Support MoLME to organise On-the-spot check/ field visits to PVETs, ATCs and other structures under MoLME

Outcome 4Output 4.1Pending / 2026-27€14,328
MR
4.1.3.4ACTIVE

Activity 4.1.3.4. Carrying out tests for the IMS use and provide feedback to the service providers

Outcome 4Output 4.1Pending / 2026-27€10,746
GN
4.1.4.1ACTIVE

Activitt 4.1.4.1. Preparation of manuals

Outcome 4Output 4.1Pending / 2026-27€41,584
CM
4.1.4.2ACTIVE

Activity 4.1.4.2. Delivery of trainings

Outcome 4Output 4.1Pending / 2026-27€41,584
TR
4.1.4.3ACTIVE

Activity 4.1.4.3. Providing online support whenever needed

Outcome 4Output 4.1Pending / 2026-27€20,792
OP
4.2.1.1DELETED

Activity 4.2.1.1. Desk review on similar digital platforms for PVET curricula

Outcome 4Output 4.2Removed (Add 3)€22,400
No evidence family
4.2.1.2DELETED

Activity 4.2.1.2. Delivery of training to MoLME staff on effective digital PVET provision (presentation of the best/promising practices)

Outcome 4Output 4.2Removed (Add 3)€22,400
No evidence family
4.2.1.3DELETED

Activity 4.2.1.3. Assessment of the existing institutional technologies to host the platform and identify needs to move towards digital platform

Outcome 4Output 4.2Removed (Add 3)€22,400
No evidence family
4.2.1.4DELETED

Activity 4.2.1.4. Identification of the solution partners who can offer quality digital learning platforms

Outcome 4Output 4.2Removed (Add 3)€22,400
No evidence family
4.2.1.5DELETED

Activity 4.2.1.5. Organisation of workshop to discuss the findings and clarify the expectations on the platform

Outcome 4Output 4.2Removed (Add 3)€22,400
No evidence family
4.2.2DELETED

Activity 4.2.2.1 Preparation of technical specification document

Outcome 4Output 4.2Removed (Add 3)€72,000
No evidence family
4.2.2DELETED

Activity 4.2.2.2 Preparation of tender dossier for procuring ICT equipment

Outcome 4Output 4.2Removed (Add 3)€72,000
No evidence family
4.2.3.1DELETED

Activity 4.2.3.1. Assisting MoLME for tendering process (evaluation of the bids, selection of best service providers etc.)

Outcome 4Output 4.2Removed (Add 3)€12,800
No evidence family
4.2.3.2DELETED

Activity 4.2.3.2. Following up the ICT equipment procurement and establishment at the relevant Primary VET institutions and Adult Training Centres

Outcome 4Output 4.2Removed (Add 3)€12,800
No evidence family
4.2.3.3DELETED

Activity 4.2.3.3. Supporting MoLME to organise On-the-spot check/ field visits to PVETs, ATCs and other structures under MoLME

Outcome 4Output 4.2Removed (Add 3)€34,000
No evidence family
4.2.3.4DELETED

Activity 4.2.3.4. Carrying out tests for the equipment and provide feedback to the service providers

Outcome 4Output 4.2Removed (Add 3)€4,400
No evidence family
5.1.1.1ACTIVE

Activity 5.1.1.1. Analysis of the national standards

Outcome 5Output 5.1Completed€75,000
MT
Drive folder
5.1.1.2ACTIVE

Activity 5.1.1.2. Conducting field visits and meeting with the institutions managers, teachers and students to assess the needs

Outcome 5Output 5.1In Process€150,000
EVMR
Drive folder
5.1.1.3ACTIVE

Activity 5.1.1.3. Developing Technical Specifications and a Tender Dossier based on the needs and national standards

Outcome 5Output 5.1Pending / 2026-27€69,200
CM
5.1.2.1ACTIVE

Activity 5.1.2.1. Supporting MoLME to organise Field visits/on-the spot checks (quarterly)

Outcome 5Output 5.1Pending / 2026-27€70,000
MR
5.1.2.2ACTIVE

Activity 5.1.2.2. Supporting MoLME to prepare monitoring reports

Outcome 5Output 5.1Pending / 2026-27€30,000
OP
6.1ACTIVE

Output 6.1 Monitoring and reporting on the Budget Support Programme

Outcome 6Output 6.1In Process€140,000
SP
Drive folder

Source documents

Reference material for the reporting dashboard.

Weekly PM conceptconcept
Evidence Map v0.1activity-master
Team Leader Dashboard Recommendationrecommendation